Description
        Notification Requirements Summary
STEP 1: UST Decommissioning/Change-in-Service 30-DAY NOTICE Form
MUST be submitted to your local DEQ regional office a minimum of 30 DAYS BEFORE STARTING any decommissioning work.
STEP 2: Telephone Notification Before Starting Decommissioning Work
MUST call your local DEQ regional office 3 DAYS BEFORE STARTING any decommissioning work.
STEP 3: UST Decommissioning Checklist and Site Assessment Report
MUST be submitted to your local DEQ regional office WITHIN 30 DAYS AFTER COMPLETION of the decommissioning or change-in-service.
    
    
        
Duration
        varies
    
    
        
Renewal Information
        None
    
    
        
Duplicate License Requirements
        None
    
    
 
Prerequisites and Requirements
    
Prerequisites
    All annual compliance fee invoices must be paid.
    
Required Documentation
    Within 30 days of completion of the field work the permittee must complete and submit to the Department a permanent closure checklist and site assessment report signed by the owner, permittee and service provider.
    
Examination Information
    None
    
Continuing Education Requirements
    None
    
Bonding Requirements
    None
    
Insurance Requirements
    A financial responsibility mechanism must be continuously maintained until tank is permanently closed.
    
Other Information
    None
Statutes, Administrative Rules, Ordinances
    
Other Detail Information
    
 Back to Top