Tank, Underground Storage Tank Decommissioning and Change in Service Last updated 06/10/2024

Print this page Back to search results

Apply

Fees

License Fee Description Exemptions
$0.00
None

Description

Notification Requirements Summary
STEP 1: UST Decommissioning/Change-in-Service 30-DAY NOTICE Form
MUST be submitted to your local DEQ regional office a minimum of 30 DAYS BEFORE STARTING any decommissioning work.
STEP 2: Telephone Notification Before Starting Decommissioning Work
MUST call your local DEQ regional office 3 DAYS BEFORE STARTING any decommissioning work.
STEP 3: UST Decommissioning Checklist and Site Assessment Report
MUST be submitted to your local DEQ regional office WITHIN 30 DAYS AFTER COMPLETION of the decommissioning or change-in-service.

Duration

varies

Renewal Information

None

Duplicate License Requirements

None

Processing Time

Processing Time Description
1 Month

Prerequisites and Requirements

Prerequisites

All annual compliance fee invoices must be paid.

Required Documentation

Within 30 days of completion of the field work the permittee must complete and submit to the Department a permanent closure checklist and site assessment report signed by the owner, permittee and service provider.

Examination Information

None

Continuing Education Requirements

None

Bonding Requirements

None

Insurance Requirements

A financial responsibility mechanism must be continuously maintained until tank is permanently closed.