Tank, Underground Storage Tank Decommissioning and Change in Service
Last updated 06/10/2024
Print this page
Back to search results
Apply
Fees
License Fee |
Description |
Exemptions |
$0.00 |
|
None
|
Description
Notification Requirements Summary
STEP 1: UST Decommissioning/Change-in-Service 30-DAY NOTICE Form
MUST be submitted to your local DEQ regional office a minimum of 30 DAYS BEFORE STARTING any decommissioning work.
STEP 2: Telephone Notification Before Starting Decommissioning Work
MUST call your local DEQ regional office 3 DAYS BEFORE STARTING any decommissioning work.
STEP 3: UST Decommissioning Checklist and Site Assessment Report
MUST be submitted to your local DEQ regional office WITHIN 30 DAYS AFTER COMPLETION of the decommissioning or change-in-service.
Duration
varies
Renewal Information
None
Duplicate License Requirements
None
Prerequisites and Requirements
Prerequisites
All annual compliance fee invoices must be paid.
Required Documentation
Within 30 days of completion of the field work the permittee must complete and submit to the Department a permanent closure checklist and site assessment report signed by the owner, permittee and service provider.
Examination Information
None
Continuing Education Requirements
None
Bonding Requirements
None
Insurance Requirements
A financial responsibility mechanism must be continuously maintained until tank is permanently closed.
Other Information
None
Statutes, Administrative Rules, Ordinances
Other Detail Information